Interconnect Assembly Procedure Draft
DFBX – D1 (LBX) Interconnect Procedure 5520-OP-333727
January 20, 2006
Version: 2.0
DFBX – D1 (LBX) Interconnect
Procedure
Reference Drawings:
Interconnection D1 to DFBX Assembly
(14130017)
DFBX – LBX Interface Specification
(LHC-DFBX-ES-0230)
DFBX Connections to D1
(24C3236, IR2L & IR8L)
(24C3246, IR2R & IR8R)
Note: This procedure is based on BNL document SMD-LHC-3001. By: Jamie Blowers, Phil Pfund
Technical Division, Fermilab
Page 1 of 14
DFBX – D1 (LBX) Interconnect Procedure 5520-OP-333727
January 20, 2006
Version: 2.0
Dwg Quantity Description Number Rev Unit Size Required
Dipole magnet assembly (D1) Tested 14060005 1 ,
3. Vacuum Vessel Bellows (24 inch) 14130001 1 4. Cap, Xb line 14130019 1 5. Instrumentation Board 14130016 1 6. M/C line bellows 14130024 1 7. Cap, CYt 1.9k transfer line 14130022 1 8. Upper heat shield 14130011 1 9. Lower heat shield 14130015 1 10. Instrumentation sleeve 14130018 1
12130080-11. Splice bar, two holes 2 05
12. Fiberglass tape 12010135 As req. 13. MLI blanket assy, inner pipes 14130007 1 14. MIL blanket assy, outer pipes 14130008 1
14130010-15. MLI blanket assy, heat shield 1 01
14130010-16. MLI blanket assy, heat shield 1 02
MS24630-17. Rivet 4 73
MS24630-18. ?-28 tapping pan screw 46 73
19. Solder (paste) 12010069 A/R
12020421-20. Solder (ribbon) A/R 03
Page 2 of 14
DFBX – D1 (LBX) Interconnect Procedure 5520-OP-333727
January 20, 2006
Version: 2.0
12010181-21. Polyamide insulation film A/R 20
22. Persistent ring, CY & CYt lines 14130027 1 23. Persistent ring, E1 line 14130028 1
Persistent ring, E2 line MB 432021 1
Transition piece, E2 line MB 432022 1
14130029-24. Persistent ring, XB & XBt lines 1 01
25. Filler bar 14130031 2 26. Persistent ring, C line 14130025 1 27. Persistent ring, C’ line 14130026 1
12130013-28. Channel insulator 2 01
12130013-29. Channel insulator 1 02
12010070-30. Solder (round wire) 1 01
14130029-32. Persistent ring, XB & XBt lines 1 02
33. Kevlar string MA 369912 A/$
O-ring (CERN-supplied) 1
Tooling
Bus splice fixture MC 430189
Page 3 of 14
DFBX – D1 (LBX) Interconnect Procedure 5520-OP-333727
January 20, 2006
Version: 2.0
GENERAL NOTES:
, All screws installed in the vacuum and cryogenic space must have some form of
additional protection from working themselves loose during thermal cycling. The use
of Loctite 242 or 245, or Stycast is recommended for this purpose.
(Complete Above Ground)
1.0 Bolts and washers from the vacuum vessel end can need to be retained and re-
installed at the end of this procedure.
2.0 Fabricate the M/C line bellows assembly. This should include shortening the cuff of
the M/C line bellows by 10mm, and then welding the adapter (no part number) to
the M/C line bellows (14130024).
3.0 Add the appropriate features to the M/C line bellows, as per the CERN-defined
drawing(s).
4.0 Install and weld the transition piece (MB-432022) to the e2 line on the D1 magnet. 5.0 Cut the heat shield assembly (upper 14130011, lower 14130015) from 853 to 800
mm. Part 14130011 can be shortened by removing 53 mm from the non-featured
end. Part 14130015 can be shortened by removing 53mm from the D1 end, and then
redrilling the holes according to drawing 14130012.
6.0 Fabricate the large Multi-Layer Insulation (MLI) inner and outer blankets that wrap
over the pipe group (14130007 & 14130008, items 13 & 14 on parts list) on a
suitable table prior to their need. They are not provided in the interconnect parts kit.
However, drawings for their fabrication are provided. These blankets extend for the
length of the interconnect.
7.0 Fabricate the large Multi-Layer Insulation (MLI) inner and outer blankets for the
heat shield (14130010-01 & 14130010-02, items 15 & 16 on parts list) on a suitable
table prior to their need. They are not provided in the interconnect parts kit.
However, drawings for their fabrication are provided. NOTE: these blankets may
need to be adjusted in length in step 17.
8.0 Install the CERN-supplied Beam Screen assemblies per the CERN drawings listed
below.
Page 4 of 14
DFBX – D1 (LBX) Interconnect Procedure 5520-OP-333727
January 20, 2006
Version: 2.0
CERN Drawings
, Beam Vacuum Interconnects Assembly Type IT 7 IR Right (LHCLVIKK0002)
, Beam Vacuum Interconnects Assembly Type IT 8 IR Right (LHCLVIKK0003)
, Beam Vacuum Interconnects Assembly Type IT 7 IR Left (LHCLVIKK0004)
, Beam Vacuum Interconnects Assembly Type IT 8 IR Left (LHCLVIKK0005) 9.0 Caps for XB/XBt and CY/CYt could be installed and welded above ground or
below ground (steps 18 and 19 of this procedure).
NOTES:
(1) Connection or capping of the XB & XBt lines is dependent on the magnet?s
installation location. Refer to Section G-G and Section C-C, Sheet 2 of drawing
14130017.
(2) Section C-C of drawing 14130017 for IR2L & IR8L should call out use of Item
32, not Item 24.
(Complete before setting units into position)
10.0 Insert the large O-ring (CERN-supplied) into the groove on the sliding flange.
Detach and slide back the sliding flange on the vacuum vessel. Install the large
vacuum vessel bellows (14130001) over the end of the D1 magnet and store there
until the interconnection work is nearly complete. Take precautions to avoid
internal and external damage to the convolutions.
11.0 Install the M/C line bellows assembly (modified 14130024) over the roll-back
flange on MBX1 line of the DFBX. Slide the bellows back and store over the tube
to provide access to the bus interconnect region.
12.0 Install the instrumentation sleeve (14130018), over the MBX2 line on the DFBX,
and slide back for storage.
13.0 XB/XBt lines preparation.
NOTES:
(1) Connection or capping of the XB & XBt lines is dependent on the magnet?s
installation location. Refer to Section G-G and Section C-C, Sheet 2 of drawing
14130017.
(2) Section C-C of drawing 14130017 for IR2L & IR8L should call out use of Item
32, not Item 24.
Page 5 of 14
DFBX – D1 (LBX) Interconnect Procedure 5520-OP-333727
January 20, 2006
Version: 2.0
13.1 Install the persistent rings (14130029-01 or 14130029-02 as appropriate), on
the correct pipes. DO NOT weld.
14.0 C line preparation.
NOTE: Refer to Section J-J on Sheet 2 of drawing 14130017.
14.1 Install the persistent rings (14130025), on the C pipe. DO NOT weld.
(Complete Below Ground)
15.0 M/C (bus) line splices.
NOTE: When warm, the D1 lines will be nominally 1.7mm higher than the mating lines on the DFBX. These will line up upon cool-down.
NOTE: The bus bars on the D1 magnet extend out from the M/C line. They are labeled “A” and “B” to indicate polarity in order to produce the desired field direction. Positive current flowing into bus bar “A” produces a positive (upward)
dipole field.
15.1 Pre-tin all leads to be spliced with solder made of 96% tin/4% silver. 15.2 Refer to Detail K on Sheet 3 of assembly drawing 14130017. Form the
magnet and DFBX superconductor cables as shown, placing the DFBX
superconductor on the outside. It may be necessary to trim and dress the
leads to achieve the 127 mm splice overlap. Place flux and silver/tin solder
ribbon (flattened round wire solder) between the two cables that make up
the “A” cable pair, and a second ribbon between the two cables that make up
the “B” cable pair.
15.3 Similarly, form the copper stabilizer ends from the DFBX over the
superconductors as shown. Install flux and solder ribbons under the “A” and
“B” legs of stabilizer cable.
15.4 Install the 2-hole splice bars (12130080-05) onto the end of the D1 bus.
Solder to the bus (the rivets do not get peened over, but are held by the
solder only). Allow to cool.
15.5 Place flux and solder ribbon on the inside surface of each solid stabilizer
(between it and the DFBX stabilizer cable).
Page 6 of 14
DFBX – D1 (LBX) Interconnect Procedure 5520-OP-333727
January 20, 2006
Version: 2.0
15.6 Insert the bus splice assembly into the soldering fixture (MC-430189).
Screw the top of the fixture around the splice area.
15.7 If desired, add an additional temperature measuring device (e.g. handheld
thermocouple).
15.8 Turn on resistive heaters, and wait for the solder to melt, while monitoring
the temperature. Tighten screws as the solder is softening, so that the fixture
is completely closed when the solder is completely melted. When the solder
has melted, turn off the heater controller. The solder typically melts at about
220? C, but the temperature should be held at 235?C for one minute. Do not
allow the temperature to exceed 240?C.
15.9 Monitor the temperature during cool-down, and let splice cool to ~ 40?C. To
monitor the temperature, unplug the heating element, and then turn the
controller back on.
15.10 After cooling (to ~ 40?C), remove the splices from the fixture. NOTE: It is
easiest to remove the splices while the fixture is a little warm, so it is
best not to let it cool to room temperature before removing the leads
from the fixture.
15.11 Clean exterior of splices with Tech spray and Scotch Brite or equivalent.
Wipe down with Kay-dry or equivalent. Check especially the areas beyond
the actual joint area for possible “wicking” of flux.
15.12 Perform electrical check for proper isolation of bus bar “A” from bus bar
“B”.
15.13 Install two Nomex insulator channels (12130013-01) in the open joint area
between bus bar “A” and bus bar “B”. Butt together these two pieces at the
approximate center of the soldered joint and apply Kapton tape to maintain
alignment of the channels and prevent the butt joint from overlapping. 15.14 Install the single Nomex insulator channel (12130013-02) over the previous
two channels. Center this channel over the butt joint between the other two
channels.
15.15 Visually inspect the partially insulated joint for any possible voltage creep
problems.
15.16 Wrap the entire joint using Kapton tape and fiberglass tape, 50% overlap for
each material. The tapes should extend for the entire length as dimensioned
in Detail K on sheet 3 of assembly drawing 14130017, starting on the G-10
conduit of the D1 bus and enclosing the wrap on the DFBX bus.
Page 7 of 14
DFBX – D1 (LBX) Interconnect Procedure 5520-OP-333727
January 20, 2006
Version: 2.0
15.17 Wrap entire splice bundle with Kevlar string (MA-369912, or equivalent) in
a similar fashion to cartoon below (figure 15.17-A). The spacing between
each loop should be ~ 1.5 cm, and the string should be pulled tightly around
the splice bundle. Apply Loctite to each cross-over to hold the string in
place. The colors of the string in the cartoon below (figure 15.17-A) show
the way in which the string is wrapped, but the string should be one
continuous piece, as much as is possible.
Apply Loctite.
Spacing between loops
should be ~ 1.5 cm.
Figure 15.17-A
15.18 Perform electrical check of completed bus to CERN procedures.
16.0 i (instrumentation) splices.
NOTE: The instrumentation wiring is located within the D1 i stub, which extends
from the end volume face. Refer to Section F-F on sheet 2 of drawing 14130017 for details of the instrumentation connection.
16.1 Position the instrumentation board (14130016) within the open area between
D1 and the DFBX. The board will eventually be captured inside the
instrumentation sleeve, but during wiring it will need to be supported
externally.
16.2 Referring to the pin connection callouts on the schematic (Section F-F on
page 3 of 14130017, or drawing 14130016. Note number 4 of drawing
14130017 refers to part „31?, which does not exist in the parts list), route the
labeled leads to be connected between D1 and the DFBX to the correct pin
number in the instrumentation board. A suggested wire routing method is
shown in Section F-F, but actual practice may dictate other routing
alternatives.
16.3 Solder each connection using silver/tin round wire solder.
Page 8 of 14
DFBX – D1 (LBX) Interconnect Procedure 5520-OP-333727
January 20, 2006
Version: 2.0
NOTE: For installation of magnet D1L105 in IR8R only, a temperature
sensor must be installed on the instrumentation board as a replacement for
the failed yoke-temperature sensor (Waiver M0272). Holes have been
provided on all four boards for this particular installation. The sensor to be
installed is to be a calibrated CERNOX sensor manufactured by Lake Shore,
Westerville, Ohio, USA. It is not provided in the parts kit. 16.4 Secure wires to board at tie points indicated using Kevlar cord (CERN-
supplied). Secure knot using epoxy (CERN-supplied).
16.5 Perform electrical tests to CERN procedures after all connections are
complete.
17.0 M/C (bus) line welding.
17.1 Using the CERN-supplied tooling, compress the M/C line bellows 20 mm.
Slide the M/C line bellows back over the completed bus joint. Align the end
cuffs of the bellows with the flanges. Further extension or compression of
the bellows (?3 mm) is acceptable if required to provide a weldable edge
joint.
17.2 Tack weld the bellows to the flanges. Complete the welding to produce a
leak-tight joint per section A-A, sheet 1, of print 14130017.
18.0 i (instrumentation) line welding.
18.1 Slide the instrumentation sleeve over the completed interconnect. Tack
weld the sleeve to the flanges, then complete the weld per Section F-F, sheet
2 of 3, of drawing 14130017.
18.2 Perform electrical tests to CERN procedures again after welding is complete.
19.0 CY & CYt line preparation
NOTE: Connection or capping of the CY & CYt lines is dependent on the magnet?s
installation location. Refer to Section A-A and Section E-E, Sheet 2 of drawing 14130017.
19.1 Install the cap (14130022) and persistent ring (14130027) on the correct
pipes. Complete ONLY the weld of the cap. DO NOT weld the persistent
ring.
Page 9 of 14
DFBX – D1 (LBX) Interconnect Procedure 5520-OP-333727
January 20, 2006
Version: 2.0
20.0 XB & XBt line preparation
NOTES:
(1) Connection or capping of the XB & XBt lines is dependent on the magnet?s
installation location. Refer to Section G-G and Section C-C, Sheet 2 of drawing
14130017.
(2) Section C-C of drawing 14130017 for IR2L & IR8L should call out use of Item
32, not Item 24.
20.1 Install the cap (14130019) on the correct pipe. Complete ONLY the weld of
the cap.
21.0 C? line preparation
NOTE: Refer to Section J-J and Section I-I, Sheet 2 of drawing 14130017.
21.1 Install the persistent ring (14130026), on the C? pipe, respectively, but DO
NOT weld.
22.0 Cold mass pipe connections and welding
22.1 Locate the pipes on the DFBX that connect to the respective pipes on the D1
magnet. Slide the ends of the pipes over the persistent rings on the mating
pipes. The CY/CYt, XB/XBt and C/C? pipes should now be physically
connected to the DFBX.
22.2 Weld the CY/CYt, XB/XBt and C/C? pipes by consuming the ridge on each
persistent ring as per Sections A-A/E-E, G-G/C-C and J-J/I-I of drawing
14130017. The C/C? and XB/XBt pipes will most likely NOT be weldable
using automatic equipment due to their proximity to adjacent pipes, so
manual welding will need to be used.
22.3 Pressurize and leak check the cold mass piping to CERN procedure after
welding.
23.0 D1 collection pot temperature sensor connections.
Page 10 of 14
DFBX – D1 (LBX) Interconnect Procedure 5520-OP-333727
January 20, 2006
Version: 2.0
NOTE: There are four four-wire RTD bundles coming out of the DFBX. Only two bundles are used at any single tunnel location (i.e. two locations connect to the D1 using PS1 and PS2, and the other two locations connect to PS3 and PS4). 23.1 Using the appropriate configurations, as defined in the schematics listed
below, solder the appropriate D1 phase separator temperature sensor wires
to the matching wires from the DFBX.
Location LBNL drawing (CERN drawing number)
IR2L 25I6156 LHCDFBX_0032
IR2R 25I6166 LHCDFBX_0033
IR8L 25I6196 LHCDFBX_0036
IR8R 25I6206 LHCDFBX_0037
24.0 Heat shield pipe preparation, connection and welding
NOTE: Refer to Section D-D and Section H-H, Sheet 2 of drawing 14130017, for the e1 and e2 pipes. The e2 line uses a different persistent ring than is identified on the drawing.
24.1 Install the persistent ring (14130028) on the e1 pipe, but DO NOT weld.
2 Install the persistent ring (MB-432021) on the e2 line, but DO NOT weld. 24.
24.3 Join the mating piping from the DFBX to the e1 and e2pipes. Weld the
pipes by consuming the ridge on each persistent ring, as per Sections H-H
and D-D of drawing 14130017.
24.4 Pressurize and leak check the heat shield piping after welding.
25.0 Insulating connected pipes
NOTE: The M/C, i, CY , and CYt lines must be individually insulated across the interconnect region.
25.1 For one of the four pipes listed above, fabricate four 8-layer blankets that
will wrap around the uninsulated length of the pipe (these blanket
assemblies are not defined in a drawing, nor are they called out in drawing
14130017). Consider the largest diameter to be encircled (e.g., over
Page 11 of 14
DFBX – D1 (LBX) Interconnect Procedure 5520-OP-333727
January 20, 2006
Version: 2.0
bellows). The outer blankets need to encompass the inner ones, but the
blankets do not need to fit tightly on the pipes and can be “bunched” a bit.
25.2 Wrap one blanket around the pipe. Butt together the seam where the blanket
edges join and apply aluminum tape to hold in place. Install the second 8-
layer blanket so that its seam is 90º from the first.
25.3 Install the second, third and fourth 8-layer blankets in the same way, taping
the seam. The seams should always be 90º away from the previous layer. 25.4 Repeat the previous three steps for each of the other three pipes to be
insulated.
25.5 Install the pipe blankets around the entire group of pipes as shown on the
drawing. Locate the joints near the bottom to reduce strain on the joints, but
stagger the joints. The seam may be overlapped rather than butted for
strength and ease of installation. Secure the joints with aluminum tape.
NOTE: To install the blankets around the top of the cold mass (under the
heat shield), the heat shield will need to be temporarily compressed laterally
in order to create enough room vertically to slide the blankets under the
shield. A large hydraulic c-clamp or other suitable means will be needed to
do this. Do not permanently distort the shape of the heat shield.
26.0 Heat Shield Installation
NOTE: The upper and lower heat shield interconnect sections fit over and attach to the shield of the D1 magnet. Refer to Section A-A, sheet 1, of drawing 14130017. 26.1 Install the lower shield section first. Make a “dry fit-up” to determine that
the part fits properly. Correct any problem areas now.
26.2 The lower (and upper) interconnect shield is cooled via conduction to the
shield in D1. To enhance thermal contact between the two parts, apply a
layer of Apiezon N to the overlapping surfaces before they are mechanically
fastened.
26.3 Make the final installation by driving the self-tapping screws through the
interconnect shield into the D1 shield at the holes provided. Make certain
there is good thermal contact between the two parts. Be sure to apply Loctite
(or equivalent) to all screws.
Page 12 of 14
DFBX – D1 (LBX) Interconnect Procedure 5520-OP-333727
January 20, 2006
Version: 2.0
26.4 Repeat the previous three steps for the upper shield section (again, be sure to
apply Loctite, or equivalent, to all screws). Make sure that no thermal
insulation inside the shield sections will be resting on or close to the
longitudinal joint, since this joint must be welded together. If inside contact
cannot be prevented, a ceramic blanket (CERN-supplied) will need to be
installed at the troublesome locations, such blanket(s) remaining inside the
interconnect.
26.5 Weld the longitudinal joint between the upper and lower parts per drawing
14130017. Intermittent weld joint is acceptable.
27.0 Insulating the Heat Shield
27.1 Check the axial length between the blankets on the D1 and the DFBX to
which the interconnect blankets will mate, making any adjustments in the
blanket drawing dimensions as required. As installed the blanket length
along the axis of the interconnect should be sufficient to cause slight
compression at its ends. This will allow for contraction motion during
cooldown, preventing the circumferential joints at the ends from opening.
Make any necessary adjustments to the blankets.
27.2 Wrap the inner blanket over the heat shield. As was done for the pipe
blankets, locate the joint to one side near the bottom to reduce strain on the
joint. The longitudinal seam may be overlapped rather than butted for
strength and ease of installation. Secure the joint with aluminum tape. 27.3 Secure the two circumferential joints at the ends that abut the D1 and DFBX
blankets using aluminum tape.
27.4 Wrap the outer blanket over the inner one. Stagger the location of the joint
relative to the inner joint. The longitudinal blanket seam may be overlapped
rather than butted for strength and ease of installation. Secure the joint with
aluminum tape.
27.5 Secure the two circumferential joints at the ends using aluminum tape.
Page 13 of 14
DFBX – D1 (LBX) Interconnect Procedure 5520-OP-333727
January 20, 2006
Version: 2.0
28.0 Final Interconnect Closure
28.1 Perform electrical tests on the interconnect to CERN procedures before the
mechanical closure is made.
28.2 Slide the large bellows from D1 where stored, bringing it over the
interconnect space to join the D1 vacuum vessel to the DFBX. Support the
bellows properly so as not to damage the convolutions during the sliding. 28.3 Bolt the sliding flange to the D1 magnet?s mating flange section using the
bolts and washers which were previously installed on the end dome. 28.4 Clamp the bellows ends to the mating flanges on the D1 and the DFBX
using the claw clamps (CERN-supplied).
28.5 Perform a vacuum leak check of the insulating vacuum space if all other
openings into the vacuum space have been previously closed.
Page 14 of 14
本文档为【Interconnect Assembly Procedure Draft】,请使用软件OFFICE或WPS软件打开。作品中的文字与图均可以修改和编辑,
图片更改请在作品中右键图片并更换,文字修改请直接点击文字进行修改,也可以新增和删除文档中的内容。
该文档来自用户分享,如有侵权行为请发邮件ishare@vip.sina.com联系网站客服,我们会及时删除。
[版权声明] 本站所有资料为用户分享产生,若发现您的权利被侵害,请联系客服邮件isharekefu@iask.cn,我们尽快处理。
本作品所展示的图片、画像、字体、音乐的版权可能需版权方额外授权,请谨慎使用。
网站提供的党政主题相关内容(国旗、国徽、党徽..)目的在于配合国家政策宣传,仅限个人学习分享使用,禁止用于任何广告和商用目的。