第8部分:配网工程
配网架空线路开关配电自动化终端安装作业指导书
编码:PWZDH-03
目次
1适用范围······················································································································································401
2编写依据······················································································································································401
3作业流程图···················································································································································401
4安全风险辨析与预控···································································································································402
5作业准备························································································································································13
6作业方法··························································································································································6
7质量控制措施及检验
标准
excel标准偏差excel标准偏差函数exl标准差函数国标检验抽样标准表免费下载红头文件格式标准下载
·······························································································································9
1适用范围
1.1电压等级
35kV及以下配网工程。
1.2电气类别架空线路柱上开关配电自动化终端安装。
2编写依据
表2编写依据
序号
引用资料名称
1
GB50171—1992《电气装置安装工程盘、柜及二次回路结线施工及验收
规范
编程规范下载gsp规范下载钢格栅规范下载警徽规范下载建设厅规范下载
》
2
DL/T5161.1—2002《电气装置安装工程质量检验及评定规程第1部分:通则》
DL/T5161.8—2002《电气装置安装工程质量检验及评定规程第8部分:盘、柜及二次回路结线施工质量检验》
3
Q/CSG10017.2—2007《110kV~500kV送变电工程质量检验及评定标准第2部分:变电电气安装工程》
4
Q/CSG11105—2008《南方电网工程施工工艺控制规范》
5
《中国南方电网有限责任公司基建工程质量控制作业标准(WHS)》
3作业流程图
图3作业流程图
4安全风险辨析与预控
4.1配网架空线路开关配电自动化终端安装作业前,施工项目部根据该项目作业任务、施工条件,参
照《电网建设施工安全基准风险指南》(下简称《指南》)开展针对性安全风险评估工作,形成该任务的
风险分析表。
4.2按《指南》中与配网架空线路开关配电自动化终端安装作业相关联的《电网建设安全施工作业票》
(编码:PWZDH-03-01/01),结合现场实际情况进行差异化分析,确定风险等级,现场技术员填写安全施工作业票,安全员审核,施工负责人签发。
4.3施工负责人核对风险控制措施,并在日站班会上对全体作业人员进行安全交底,接受交底的作业人员负责将安全措施落实到各作业任务和步骤中。
4.4安全施工作业票由施工负责人现场持有,工作内容、地点不变时可连续使用10天,超过10天须重新办理作业票,在工作完成后上交项目部保存备查。
表4.1作业任务安全基准风险指南
序号
危害名称
风险种类
风险等级
风险控制措施
1
不规范使用梯子
坠落
低风险
1.使用合格梯子;
2.正确使用梯子;
3.必要时设专人扶梯
2
高处作业没有正确使用安全带
坠落
中等风险
高处作业必须正确使用安全带
3
施工区域没有安全围蔽
摔绊扭伤坠落打击
中等风险
施工区域必须做好安全围蔽及警示标志措施,晚上设置夜间警示灯,防止外人误入工作区域
4
施工用电不规范
触电
中等风险
1.加强使用前及使用过程中的检查,保护零线与工作零线不得混接,开关箱漏电保护器灵敏可靠,漏电保护装置参数应匹配;
2.用电管理和检修维护必须规范,并由专业电工进行,配电箱必须上锁,并采取防雨措施;
3.工作间断时切断电源;
4.必须使用符合要求的线缆,并做好防破损
措施
5
高空作业时工器具坠落
打击
中等风险
1.工具装进工具袋;
2.工具、材料用绳索传递;
3.施工平台临边范围安装踢脚板
6
电流互感器二次侧开路
触电
中等风险
严格按照
设计
领导形象设计圆作业设计ao工艺污水处理厂设计附属工程施工组织设计清扫机器人结构设计
图纸接线及调试,做好回路检查工作
7
剥切控制电缆外护套时失手割伤手脚
割伤
低风险
1.剥切外护套时需集中精神,正确操作防止割伤;
2.使用专用工具
8
剥切电缆外皮时损伤电缆线芯
设备破损
低风险
对工作人员进行工艺培训,提高施工工艺,选择专用工具
9
临时拆除的线芯未进行绝缘处理
触电
低风险
临时拆除的线芯未进行绝缘处理
10
遥控调试两端未设专人监护
打击触电
低风险
遥控调试时两端应设专人监护、保持两端通信畅通
11
遥测调试时操作不当
触电
低风险
遥测调试时两端应设专人监护、保持两端通信畅通
5作业准备
5.1作业前施工条件
表5.1作业前施工条件
序号
项目
内容
执行人
说明
1
任务单
根据本单位实际设置内容(包含本项工作)
本工序施工负责人
经审批
2
图纸
设备变更单、设计图纸
本工序施工负责人
经审批
3
预算材料表
含主、辅材
本工序施工负责人
经审批
4
施工
方案
气瓶 现场处置方案 .pdf气瓶 现场处置方案 .doc见习基地管理方案.doc关于群访事件的化解方案建筑工地扬尘治理专项方案下载
施工措施、安全技术交底(项目部级)
本工序施工负责人
经审批
5
相关证照
根据需要办理涉及进入工作场所的手续、证件
本工序施工负责人
有效
6
确认现场施工条件
柱上式自动开关及电压互感器已安装完成。终端安装位置与高压设备、线路保持足够的安全距离
本工序施工负责人
合格
5.2人员、主要工器具及仪器仪表配置
表5.2人员、主要工器具及仪器仪表配置
序号
项目
内容
说明
1
人员配置
施工阶段
建议工作人数
现场施工负责人
现场施工质安员
技术岗位必须持有与作业工种相应、有效的上岗证,辅助工不得从事电气设备安装等专业工作
终端安装
技术工1+辅助工1
1
1
电缆敷设及接线
技术工1+辅助工1
终端调试
技术工1
2
施工内容相对应的设备材料
配电自动化终端、控制电缆、安装辅材等
(1)核对配电自动化终端及附件、材料的到位及数量;核对各项参数符合设计要求。
(2)检查配电自动化终端外观完好。
(3)收集配电自动化终端出厂证件、技术资料
3
施工内容相对应的器具、机械及工器具仪表
工器具:扳手、螺丝刀、梯子、笔记本电脑、绝缘手套、绝缘鞋、高压临时地线、高压验电笔等。
机械:车辆等
(1)根据现场情况使用的工器具、机械符合相关要求。
(2)使用仪表有计量单位检验
合格证并在合格期间内
4
完成开工程序
工作负责人向项目负责人报开工,并由项目负责人完成向监理单位开工报审手续
施工准备完成可报开工,当施工准备不足时,上报该项目负责人协调解决
6作业方法
表6作业方法
序号
项目
内容
说明
1
作业前工作
(1)现场施工负责人向进入本施工范围的所有工作人员明确交待本次施工设备状态、作业内容、作业范围、进度要求、特殊项目施工要求、作业标准、安全注意事项、危险点及控制措施、危害环境的相应预防控制措施、人员分工,并签署(班组级)安全技术交底表。
(2)工作负责人负责办理相关的工作许可手续,开工前
好现场施工防护围蔽警示措施,夜间施工的须有足够的照明。
(3)现场施工负责人组织检查确认进入本施工范围的所有
工作人员正确使用劳保用品和着装,并带领施工作业人员进
入作业现场
按安规规定佩戴统一的安全帽,统一佩戴有个人照片的作业证(或
做胸卡证),穿着统一的工作服
2
开始主要作业
现场施工负责人发出许可开工命令
3
终端安装
(1)终端安装应垂直、牢固。
(2)终端外壳采用合乎规范的导线可靠接地。
(3)终端及终端内的设备元器件必须按照统一的标准格式
进行标注。设备模块编号、用途、地址编号均要标识清晰。
(4)终端安装高度根据设计要求确定,既要方便日常维护
工作,又要与高压设备、线路保持足够的安全距离
现场施工负责人正确、安全地组织作业,现场施工质安员负责现场作业全过程的安全、质量监控
4
电缆敷设及接线
(1)根据设计要求、产品说明书接线,并做好标识。
(2)电缆穿管(PVC管或镀锌钢管,根据实际情况使用)
敷设,保持垂直、美观、牢固
现场施工负责人正确、安全地组织
作业,现场施工质安员负责现场作业
全过程的安全规范和质量跟踪
5
终端调试
(1)通信联调:设置终端通信参数与调度端匹配,测试连接状态正常。
(2)遥测量调试:输入相应参数值,用模拟设备对电流、电压等模拟量输入回路分别加入设计额定值的1/2、额定值、
1.2倍额定值进行测试,核对调度主站显示值与现场一致。
(3)遥信量调试:现场模拟遥信信号,核对调度主站显示
信号与现场一致。
(4)遥控调试:实际模拟遥控操作,检查开关分、合闸动
作正确性。
(5)保护功能调试:根据定值,在二次回路加入对应的越
限值,检验保护动作是否正确
7质量控制措施及检验标准
7.1质量控制措施
7.1.1现场负责人应根据现场情况安排技术人员负责质量监控。
7.1.2作业人员必须熟悉工程作业流程和质量检验标准;技术岗位人员必须持有与作业相应、有效的上岗
证。
7.1.3现场负责人在进行安全技术交底时必须详细介绍本作业质量控制要点、常见的质量通病及其防治措施。
7.1.4作业现场必须有经审核批准的设计图纸和
施工方案
围墙砌筑施工方案免费下载道路清表施工方案下载双排脚手架施工方案脚手架专项施工方案专项施工方案脚手架
,作业人员必须按图施工。
7.1.5施工质量检验一般按以下方式进行。质量检验一般采用三级检验制,施工队(组)对所施工的分项工程应进行100%的质量自检;项目部对所负责施工的分部工程和单位工程组织质量检查,复检比例不宜低于50%;公司对单位工程组织检查,抽检比例不宜低于20%。
7.1.6隐蔽工程施工完成以及全部工序作业完成(转序)时,必须提前24小时通知监理现场验收。
7.2质量控制点
表7.2质量控制点表单
控制点
控制方式
W
H
S
配网自动化安装工程
●
7.3检验标准
质量检验按《10kV~500kV输变电及配电工程质量验收与评定标准第8册:配网工程》中的Q/CSG表
8-7.18要求执行。
●附件1安全施工作业票
编码:PWZDH-03-01/01
工作时间
工作地点
技术员
现场安全员
现场负责人
安全风险分析及控制措施
序号
危害名称
风险种类
风险等级
风险控制措施
1
使用梯子不规范
坠落
□低风险
现场作业应严格执行相关安全规程及安全技术措施,并重点关注但不限于以下措施:
□使用合格梯子、正确使用梯子,必要时设专人扶梯。
□高处作业必须正确使用安全带。
□施工区域必须做好安全围蔽及警示标识措施,晚上设置夜间警示灯,防止外人误入工作区域。
□加强使用前及使用过程中的检查,保护零线与工作零线不得混接,开关箱漏电保护器灵敏可靠,漏电保护装置参数应匹配。
□用电管理和检修维护必须规范,并由专业电工进行,配电箱必须上锁,并采取防雨措施,工作间断时切断电源。
□施工电源必须使用符合要求的线缆,并做好防破损措施。
□工具装进工具袋,工具、材料用绳索传递。
□施工平台临边范围安装踢脚板。
□严格按照设计图纸接线及调试,做好回路检查工作。
□剥切外护套时需集中精神,使用专用工具,正确操作防止割伤。
□对工作人员进行工艺培训,提高施工工艺,选择专用工具。
□临时拆除的线芯未进行绝缘处理。
□遥控调试时两端应设专人监护,保持两端通信畅通
2
高处作业没有正确使用安全带
坠落
□中等风险
3
施工区域没有安全围蔽
摔绊、扭伤、坠落、打击
□中等风险
4
施工用电不规范
触电
□中等风险
5
高空作业时工器具坠落
打击
□中等风险
6
电流互感器二次侧开路
触电
□中等风险
7
剥切控制电缆外护套时失手割伤手脚
割伤
□低风险
8
剥切电缆外皮时损伤电缆线芯
设备破损
□低风险
9
临时拆除的线芯未进行绝缘处理
触电
□低风险
10
遥控调试两端未设专人监护
打击、触电
□低风险
11
遥测调试时操作不当
触电
□低风险